Current Roadworks - Temporary Road Closures - Bridge Closures



Please be advised that the Samuel Beckett Bridge will close to both pedestrian and vehicular traffic on the following date to facilitate its annual maintenance.
 
Tuesday 23rd July 2019, from 21:00 hours until 22:00 hours

Please click here to view a schedule of planned bridge closures up to and including 31st August 2019.

_________________________________________________________________________________________________________________________

 
Liffey Swim

A request has been received from Leinster Open Sea c/o Swim Ireland for the temporary closure of the following road to facilitate the Liffey Swim Event on the date and times listed below:
•Location 1:      Rory O’More Bridge, Dublin 8 from 08.00hrs to 17.00hrs on Saturday 3rd August 2019.
•Location 2:      Custom House Quay (from Eden Quay to Memorial Road), Dublin 1 from 08.00hrs to 18.00hrs on Saturday 3rd August 2019.

Traffic Management Plan
•Traffic on Wolfe Tone Quay wishing to travel across Rory O’More Bridge to Watling Street / Victoria Quay will be diverted via North Quays, Grattan Bridge and South Quays.
•Traffic from Eden Quay / Butt Bridge wishing to travel on Custom House Quay will be diverted via Beresford Place and Memorial Road
•Pedestrian access will be maintained.

 

Barrow Street (from Grand Canal Street to Ringsend Road), Dublin 4

A request has been received from John Sisk & Son Ltd for the temporary closure of the following road to facilitate the erection of a tower crane on the dates and times listed below:
•Barrow Street (from Grand Canal Street to Ringsend Road), Dublin 4 from 08.00hrs on Saturday 10th August 2019 to 20.00hrs on Sunday 11th August 2019.

Traffic Management Plan
•Pedestrian and local access will be maintained.






 


 


 

 
 
 
 
 

 